We are finally in the dry with the roof light recently installed and the last of the roof timber going on now. We have started to render inside to enable us to finish all internal finishes. All windows and doors are in with some small alterations to be made. We now need to take the scaffolding down to enable us to complete some external works. the final push continues.
Tuesday, 17 June 2008
Friday, 16 May 2008
The big push continues
Wednesday, 30 April 2008
A big push now needed to complete all areas
We are now at a stage with the build that requires a big push in all areas to bring the completion in before all of the students finish for their summer break. This means we will be working in several areas at once. We are currently expecting the main delivery of larch to complete the roof. Along with working on the internal works such as floor joists, electrical works and plasterboarding. All steels are now in place and the windows are due in very soon so that we can begin to render with lime and finish the building. Before the fermacell plasterboard can go up with have filled the roof with thermafleece (Lambswool) insulation and lined it with a vapour barrier. All drainage is in apart from final connections when the scaffolding comes down. So over the next seven weeks we will be looking to finish the building to a point that the trust can fit it out to their own requirements.
Friday, 28 March 2008
Roof is progressing well
Wednesday, 12 March 2008
Roof work begins
It is now time to start to push on with the roof work but recent weather has slowed up progress. although the storms have not affected the building structurally I am unable to work on the roof if there is a threat of rain as the bales are still vulnerable and require constant protection. This coupled with a sequencing issue regarding the installation of structural steel works before we can complete the structure is giving me a headache. The students are still gaining valuable experiance with a whole group of third year students constructing the main roof structure with assistance from their tutor Steve.
Friday, 15 February 2008
Walls are completed and compression begins
After a significant push by students and all involved in the project, plus a kind spell of good weather we have managed to bring the project back on programme. That being with the walls completed and under compression for the half term break. We even had students assisting the farmer to restring some bales on his farm as a significant number of the original bales were deemed unsuitable due to them getting wet. Again student accuracy amazed me again with the top ring beam being exactly square and exactly plumb over the bottom beam on all four sides. This is with a level of tolerance within 5 mm. Considering we have been using a building product as natural in size and shape as a straw bale. these pictures show the top beam in place and being staked down to the bales below. The next stage is to allign all of the bales with the beams and compree the straw over a period of a week or two. This will then be ready to install the roof.
Sunday, 10 February 2008
The walls are growing...
Good progress is being made inbetween the showers. A few bales have got wet and have had to be discarded and some replacements will be made up as quickly as possible. Nick and the students aim to get the upper ring beam in place and ratcheted down before the half term break - which starts in five days time...
Earlier this week Occombe hosted a visit by 20 farm shop operators from across the country who were attending a workshop organised by FARMA (the Farm Retail and Markets Association). The workshop was for people to find out how Occombe Farm won Best Newcomer of the Year 2008 in the annual FARMA Awards. There was great interest in the straw bale building and Nick gave a tour for the group. One delegate has gone away vowing to build the first straw bale farm shop in the country!