Tuesday, 7 October 2008




We now have a completed structure. the walls are all rendered with Lime render, the internal works are practically complete and we now only have some minor works to carry out to complete the project. Decorating the inside and out has started and is well under way, we only need to cover the tyres with a timber skirt and install the rain water goods to be able to say the building is finally complete.

Tuesday, 17 June 2008

Roof is almost finished


We are finally in the dry with the roof light recently installed and the last of the roof timber going on now. We have started to render inside to enable us to finish all internal finishes. All windows and doors are in with some small alterations to be made. We now need to take the scaffolding down to enable us to complete some external works. the final push continues.

Friday, 16 May 2008

The big push continues


We are now working on lots of build elements concurrently to try to bring the build in on time (and before the students head for the beach for the summer). This means we are working on boarding out inside as well as installing electrical trunking whilst fitting the windows and installing the larch boards to the roof outside. The lime render needs to be started soon in order for it to cure intime to decorate before the end of term. All being well we are still on target to complete before the end of term but we cannot afford any more hold ups.










Wednesday, 30 April 2008

A big push now needed to complete all areas



We are now at a stage with the build that requires a big push in all areas to bring the completion in before all of the students finish for their summer break. This means we will be working in several areas at once. We are currently expecting the main delivery of larch to complete the roof. Along with working on the internal works such as floor joists, electrical works and plasterboarding. All steels are now in place and the windows are due in very soon so that we can begin to render with lime and finish the building. Before the fermacell plasterboard can go up with have filled the roof with thermafleece (Lambswool) insulation and lined it with a vapour barrier. All drainage is in apart from final connections when the scaffolding comes down. So over the next seven weeks we will be looking to finish the building to a point that the trust can fit it out to their own requirements.























Friday, 28 March 2008

Roof is progressing well

The main roof structure is now in place apart from some steels which will be installed over the coming week. We can now start to weather proof the building in order to start work inside. The main students used in the construction of the roof is a third year group tutored by steve who have produced some very good work to add to their college assessments. As the building takes shape and we can now start fitting it out, pressure for the building to be completed also starts to build. Timing is critical especially for the rendering of the straw as rendering too early before compression is complete will result in the bond being broken between the render and the straw. Rendering too late and we will not have time for the lime to cure and the students to carry out the work as they start to complete their work at college and leave for their summer break. I am sure anybody visiting the site will agree the building is starting to look impressive in its surroundings at occombe farm.

Wednesday, 12 March 2008

Roof work begins



It is now time to start to push on with the roof work but recent weather has slowed up progress. although the storms have not affected the building structurally I am unable to work on the roof if there is a threat of rain as the bales are still vulnerable and require constant protection. This coupled with a sequencing issue regarding the installation of structural steel works before we can complete the structure is giving me a headache. The students are still gaining valuable experiance with a whole group of third year students constructing the main roof structure with assistance from their tutor Steve.


Friday, 15 February 2008

Walls are completed and compression begins


After a significant push by students and all involved in the project, plus a kind spell of good weather we have managed to bring the project back on programme. That being with the walls completed and under compression for the half term break. We even had students assisting the farmer to restring some bales on his farm as a significant number of the original bales were deemed unsuitable due to them getting wet. Again student accuracy amazed me again with the top ring beam being exactly square and exactly plumb over the bottom beam on all four sides. This is with a level of tolerance within 5 mm. Considering we have been using a building product as natural in size and shape as a straw bale. these pictures show the top beam in place and being staked down to the bales below. The next stage is to allign all of the bales with the beams and compree the straw over a period of a week or two. This will then be ready to install the roof.