Wednesday, 30 January 2008

Straw walls are on the up



Here are some images of the straw walls being constructed on site. It shows each stage from the first bale being positioned to the hazel stakes being driven in. Progress on site has been rapid with the spell of good weather helping us (for the moment). We currently have five courses of bales in place with two to go, this will happen when the scaffolding has been erected.






























Tuesday, 15 January 2008

Ring beam is almost in despite the weather

Work is almost complete on the first ring beam so that the straw can be installed. Here you can see that we are using ratchet straps to bring the beam into square. We checked the diagonal measurements which are within 10mm of each other so already a very good level of accuracy is being achieved by the college students. All carpentry students so far have been 16 or 17 years old so this does bode well for a quality workforce for the future.
We had great difficulty lifting the sections of beam over the tie down bolts but with a bit of persistance and and a few well directed hammer blows all is in place and located in the correct position over the tyres.

Sunday, 13 January 2008

600 pointy sticks arrive!


On a soaking wet day last Friday Brian Williamson and his apprentice Ruth delivered their load of pointed hazel rods, which will be used to spike the straw bales together. The rods are superbly uniform and very smart - shame they will be hidden inside the straw once the building is up!


150 bales have also arrived on site and the walls will start to go up this coming week.

Wednesday, 9 January 2008

Carpentry students get stuck in





Carpentry students begin the construction of the ring beam by cutting 18mm ply wood into strips ready to make a beam for setting the straw bales onto the foundation of tyres. These foundation students had never used this type of powered skill-saw before so they were a little apprehensive, but by the end of the day 88 strips had been cut to the correct width.




As you can see we have also erected a temporary shelter to keep out the worst of the weather.





The next stage for the carpenters is to screw it all together to form the beam as you can see here.

Thursday, 20 December 2007

Progress with tyres



Over the past week or so we have been diligently filling the tyres with 10mm chippings, the majority of the filling happened during two days on site with large groups of students working in teams to shovel and compact the stones. I required the assistance of another college staff member (Mike Prosser) to supervise these larger groups. we are now almost ready for the straw walls to go up.

You can also see in the background of this picture that we now have a site office and canteen so that we can establish the required welfare facilities on site. Untill now we have been sharing the occombe farm buildings to satisfy the CDM regulations. We can now be self sufficient on site without interfering with farm operations.

Filling tyres with stone


We are now in the position to fill all of the tyres as we now have enough to complete the foundations. The method we employed to ensure the tyres are full with chippings is to lever the inner edge of the tire with a pick axe and ram the chippings in with a blunt object (stick). We will let the chippings settle for a couple of weeks (over the christmas period) and then we will settle them more using a plate compactor topping up the tyres as required.

Wednesday, 12 December 2007

Things take shape



Here's a lovely drawing that our architect, Mark Ledgard at Stratton & Holborow has done, to show a little better what the building will look like.


Car tyres are now arriving from our friends at ATS in all the towns hereabouts, who have been collecting the right size tyres for our foundations. We have around 130 of the 180 we need and the students have been setting them out on site. It doesn't look very rural at the moment!

Other highlights - we have commissioned local Devon woodsman Brian Williamson to prepare the 570 pointed hazel stakes we will use to pin the straw bales together, and he's started work already on this, delivery expected early January when we will start on the walls. Here's a picture of Brian's apprentice, Ruth, at work in the woods cutting the hazel rods.

Today a class of College students have had a straw-bale building course on site under Nick's tuition, as a dry run prior to the real build, and have also started fabricating the wall plate out of timber. This sits between the tyres and the straw and is used to anchor everything together.


A static caravan has been manoevred onto site today. Donated by Hoburne Holiday Park in Paignton, the caravan will act as the site office for the next few months, giving the students much-needed shelter and R&R facilities during the doubtless wet Devon winter that's to come.